COMMON PLATT - DRAINAGE SURVEY - 18th - 29th AUGUST 2025

Highway drainage survey at Common Platt is programmed for 18th – 29th August, between 0930hrs & 1430hrs.
It will involve the use of 3-way temporary traffic lights at the mini-roundabout which may cause delays for the travelling public.
The working hours will be 0800hrs – 1600hrs.

Advanced warning signs will be put out on site two weeks before the work is due to commence.

Work details can be found here: https://one.network/?GB144292801